Changing a task assigned to in TFS doesn't reflect in project

Jul 26, 2007 at 4:21 PM
Hi,

If we change the task assignment to another person in a Task, this information doesn't seem to synchronized to Project Server.

Is this a bug or a feature?

Thanks
Coordinator
Jul 26, 2007 at 6:29 PM
Do you mean if you change it in a Work Item? There was a bug in the inital release where it would not flow to Project Server; however, this was fixed with the latest release. Is that the one you are using?

Thanks,
Lenny
Jul 26, 2007 at 7:36 PM
Yes. That is exactly my scenario.

We are already using the latest release. I will try to see if there are some traces in the event log about the problem.


lfenster wrote:
Do you mean if you change it in a Work Item? There was a bug in the inital release where it would not flow to Project Server; however, this was fixed with the latest release. Is that the one you are using?

Thanks,
Lenny

Jul 30, 2007 at 2:17 PM
Lenny,

Exactly the same problem for me. Reassign behaviour do not work correctly from neither PS nor TFS. I don't think I have anything strange in log. Maybe I misunderstood the scenarios, where can I read what exactly should I expect when reassign items?

::Mike